# Client onboarding documentation proposal

Fictional worked example, version 2. This is an authored revision of the page's test proposal, not evidence of an authenticated product run.

## Decision requested

Review a proposed three-week schedule for Larch Studio's onboarding documentation project. Approve it only after the operations lead and delivery owner confirm availability. The scope, one consolidated feedback round, acceptance criteria and $6,000 USD budget ceiling are unchanged. No supplier fee or commercial terms are agreed, and this document does not authorize spending or rollout.

## Objective and starting point

Larch Studio is a fictional 12-person agency whose operations lead reports onboarding instructions scattered across email and notes. The project will define a consistent process, handoff owners and exception paths.

The five anonymized past-project folders and 45-minute interview have not been reviewed. No timing or error baseline is available; there is no verified improvement, savings or revenue claim.

## Scope and deliverables

| Deliverable               | Contents                                                                                      | Acceptance check                                                                         |
| ------------------------- | --------------------------------------------------------------------------------------------- | ---------------------------------------------------------------------------------------- |
| Current-process map       | Steps, handoffs and unresolved gaps from five anonymized folders and the operations interview | Operations lead checks the map and flags gaps before drafting proceeds                   |
| Intake form specification | Required information, collection responsibilities and missing-information handling            | Client-service lead identifies what to request and from whom in both fictional scenarios |
| Kickoff checklist         | Preparation tasks, accountable roles and approval checkpoints                                 | Every handoff has an owner and completion condition                                      |
| Onboarding SOP            | Ordered steps, responsibilities and missing-information and overdue-approval escalation paths | Both walkthroughs finish without unowned handoffs or undefined escalation paths          |

The map review remains a proposed quality checkpoint. Exact owners and escalation rules require discovery and confirmation. The intake deliverable is a specification, not a deployed form.

## Exclusions

CRM changes, software implementation, integrations, legal advice and a client-facing rollout remain excluded. New requirements need a separate scope and budget decision.

## Proposed three-week plan

| Period | Proposed work                                                                                               | What must happen sooner                                                                                                                        |
| ------ | ----------------------------------------------------------------------------------------------------------- | ---------------------------------------------------------------------------------------------------------------------------------------------- |
| Week 1 | Review all five folders, hold the interview, map the process and begin drafting after map review            | Inputs and interview availability are needed early in the week; operations lead must resolve core ownership questions before drafting advances |
| Week 2 | Finish the intake specification, checklist and SOP; run the two walkthroughs; collect consolidated feedback | Client-service lead must test and operations lead must consolidate the single feedback round by the end of Week 2                              |
| Week 3 | Apply feedback, repeat affected checks and deliver the final document set for founder review                | Delivery owner and founder must reserve time for revision and acceptance within Week 3                                                         |

This moves drafting into Week 1 and testing into Week 2. It compresses elapsed time without deleting deliverables or acceptance checks. The availability requirements are proposed conditions, not commitments already made. Do not confirm the shorter schedule until the owners agree that the overlap is workable. If a dependency slips, re-plan dates rather than silently reducing scope or skipping a check.

## Responsibilities

- Operations lead: project ownership, early input access, interview, process decisions and one consolidated feedback round.
- Client-service lead: both fictional walkthroughs during Week 2 and a record of acceptance failures.
- Founder: scope, budget and final-delivery approval, including review availability in Week 3.
- Delivery owner: still to be appointed; confirms capacity for overlapping discovery and drafting, then produces the drafts and revisions.

## Budget and commercial status

The budget ceiling remains $6,000 USD. It is not a fee or approved quote. Rates, taxes, expenses and payment terms remain unconfirmed. The shorter schedule does not imply a rush fee, a discount or an approved total. Confirm the proposed total and whether the ceiling includes taxes and expenses before authorizing work.

## Assumptions and risks

- Early folder access and interview availability are required for the compressed plan. Confirm both before kickoff.
- Process disagreements must be resolved quickly enough to draft in Week 1. Record unresolved decisions instead of inventing rules.
- Testing and consolidated feedback must finish during Week 2. Late or conflicting feedback puts the three-week plan at risk.
- One feedback round remains included; extra rounds or scope require an explicit decision.
- Two successful fictional walkthroughs show usability in those scenarios only. They do not establish a measured operational improvement.

## Final acceptance and handoff

The acceptance bar is unchanged: the client-service lead must identify every handoff owner and find the missing-information and overdue-approval escalation paths in both fictional scenarios. Record failures, revise the affected text and repeat those checks before requesting approval.

Deliver the process map, intake specification, kickoff checklist, SOP, walkthrough notes and unresolved items as Markdown documents. Founder approval and a separate rollout decision are still needed.

## Questions before kickoff

1. Who is the delivery owner, and can that person support the proposed overlap?
2. What fee, tax treatment, expenses and payment terms fit the $6,000 ceiling?
3. Can the operations lead provide the folders and interview early in Week 1?
4. Can testing and one consolidated feedback round finish in Week 2, with founder review in Week 3?
5. Who confirms process owners, approves exception rules and selects the two fictional test scenarios?

## Revision record

The requested schedule changes from four weeks to a conditional three weeks. Drafting, testing and feedback move earlier. Scope, the single feedback round, budget ceiling, exclusions and acceptance criteria remain unchanged. No fee, start date, availability commitment or completed outcome has been added.